Parker Street Hotel

Featuring a 4.5 cantilever on level 6, this high-quality boutique hotel reflects its luxury location.

  • Location:

    13 Parker St, Haymarket NSW

  • Completion duration:

    18 Months

  • Completion date:

    Late 2024

  • Client:

    Forte & LFG Pty Ltd

  • Architect:

    Bates Smart / Brewster Murray

  • Building Services Engineer:

    JHA Consulting Engineers

  • Structural and Civil Engineer:

    Adams Engineers / Rincovitch

  • No. Levels

    15

High-quality boutique hotel development comprising of 174 rooms over 15 floors and a single-level basement.

Design and construction strategy has been informed by a number of pre-existing and future constraints including existing below-ground substations and easements, and a future TfNSW rail tunnel.

Features

At level 6, the building cantilevers out 4.5m of the NSW Lightrail substation to provide an enhanced amenity and vies toward the city and George St.

The design includes a combination of glazed, and masonry elements which are incorporated into a curtain wall system.